PJB Solutions were working on a listed building in Taunton when a serious safety problem arose after rot was found in the roof. The building had to be made safe and then repairs carried out. Piers were re-built, rotting timbers were replaced with fabricated metal shoes. The roof problem had the potential to seriously disrupt the project schedule. The client was delighted with the way PJB Solutions dealt with the problem and still managed to complete on time.

Doesn’t know of any other contractor who would have continued to work throughout the roof disruptions and work so well and collaboratively to meet deadlines”

 