PJB Solutions case study

Convert Factory to Warehouse and Office Environment

Warehouse new floor and lights 3

Job Convert factory to warehouse and office environment
Client BFF / Firemark
Completed March 2012
Category Industrial
Trades Electrical, plumbing, groundworks, decorating, flooring, diamond grinding. specialist cleaning
Value £75k
Description / key tasks

As a dilapidations project, PJB Solutions were required to restore and make good a factory environment at end of lease.

They were then required to convert the building to warehouse and offices ready for new client to take possession. This involved:

  • Strip electrics back to sub stations,
  • Remove old machinery,
  • Fill and cement machinery pits,
  • Diamond-grind flooring and replace with epoxy resin floor covering.
  • Deep clean internal wall and roof,
  • Clean external walls, windows and roofing,
  • Decorate all offices and factory spaces,
  • Provide and lay new carpet tiles in offices,
  • Replace toilet facilities and renovate rest rooms,
  • Remove all overhead pipe work,
  • Renovate gas space heaters and boiler,
  • Replace retaining wall to the side of the warehouse.
Challenges & successes

PJB Solutions had to work to tight timescales to make sure the facility was ready for the new lease holders; they worked around the clock to complete.

It was essential to coordinate specialist trades and equipment to keep the project on track

Testimonial
Testimonial contact